Deck formwork with an HV transmission tower beyond

Sector 02

Power Infrastructure

Civil and structural works for 132/33kV transmission substations.

A 60MVA transformer arrives on a programme fixed months earlier and sets down on a plinth whose tolerances were fixed at design stage. We have delivered earthworks design and construction, transformer and equipment foundations, geotechnical investigation, site layout and control-building structural design for substations in South-Western and North-Central Nigeria.

Our scope has also covered access roads, perimeter fencing, borehole water supply and staff quarters: the full civil envelope around the electrical works.

Voltage class
132/33kV substations
Heaviest plinth
80-tonne, 60MVA transformer
Perimeter
1,800m substation fence

Photographs (11)

From the register

No.ClientEngagementRoleStatus
01Rhuoga Energy LimitedEarthwork design and construction for a 132/33kV transmission substation, South-Western NigeriaDesign & build consultant / sub-contractorCompleted
02Rhuoga Energy LimitedDesign of a plinth foundation for an 80-tonne, 60MVA transformer at a 132/33kV substation, North-Central NigeriaDesign consultantCompleted
03Rhuoga Energy LimitedHigh-voltage transmission substation site layout designDesign consultantCompleted
05Rhuoga Energy LimitedConstruction of 1,800m perimeter fence at a transmission substationSub-contractorOngoing
16Rhuoga Energy LimitedHigh-voltage transmission substation site layout designDesign consultantCompleted
17Rhuoga Energy LimitedGeotechnical / soil investigation for a high-voltage transmission substationSub-contractorCompleted
19Rhuoga Energy LimitedConstruction of 60MVA transformer equipment foundationSub-contractorCompleted
21Rhuoga Energy LimitedStructural design of a high-voltage substation control buildingDesign sub-contractorCompleted

Next step

Tell us about your project.

Answer a few questions and send them to us on WhatsApp or email. You get a reference number straight away.

WhatsApp